Solar on an asbestos roof: the rules before any panel goes up
Many older factories, sheds and farm buildings have asbestos cement roofs. Solar can still be an option, but the rules come first and they change the cost.
Before any roof work, the site's asbestos register must be checked and the roof treated as containing asbestos if in doubt. SafeWork NSW recommends removing and replacing asbestos material likely to be disturbed before installing solar. Removing more than 10 square metres of non-friable asbestos, or any friable asbestos, needs a licensed removalist, and the installer should get a clearance certificate before starting.
The register comes first
Workplaces must identify asbestos-containing materials and record them in an asbestos register, as part of an asbestos management plan[1]. Suspected material should be treated as asbestos[1].
Remove, or work around?
SafeWork NSW recommends that asbestos material likely to be disturbed is removed and replaced with non-asbestos material before solar is installed[1]. Drilling through corrugated asbestos sheeting is a known problem, and dust controls may not be practicable on corrugated roofs[1]. Water blasting or compressed air on asbestos is prohibited[1].
Licensing and clearance
- Removing more than 10 square metres of non-friable asbestos, or any friable asbestos, must be done by a licensed removalist[1].
- If licensed removal has happened, the installer should get a clearance certificate before starting[1].
- A safe work method statement is needed for work involving asbestos or a fall risk of 2 metres or more[1].
Fragile roofs
Assume the roof is fragile unless a competent person confirms otherwise; asbestos cement sheeting can be brittle and slippery[1]. Adding rooftop solar can also change how often the roof is accessed and interfere with existing anchor points[2].
What it means for a quote
A quote for an asbestos roof should say whether it includes the asbestos assessment, removal and re-roofing, or excludes them. Re-roofing is often the biggest variable cost on these sites, and it is a chance to fit a roof that suits solar. See comparing commercial quotes.
Get your business site assessed, by email
Commercial solar depends on your roof, your tariff, your load profile and your network, so every site is looked at individually. There is no online calculator for this, on purpose.
- 12 months of electricity bills, or your smart meter interval data (NEM12)
- The site address and what the business does
- Roof type and a few photos, if you have them
Or email olly@aussiesolarinfo.com with the subject "Commercial solar enquiry".
No installer pays to appear on this site. Nothing reaches an installer unless you ask.
Common questions
Can you put solar panels on an asbestos roof?
It may be possible, but the asbestos register must be checked first, and SafeWork NSW recommends removing and replacing asbestos likely to be disturbed before installing solar.
Who can remove an asbestos roof for solar?
More than 10 square metres of non-friable asbestos, or any friable asbestos, must be removed by a licensed removalist.