Connecting business solar over 30kW: approval, protection and export limits
Up to 30kW, a business system connects much like a home one. Above it, the network has a say in the design, the timeline and how much you can export.
Above 30kW, a solar system needs written approval from the network before it is installed, and central (interface) protection under AS/NZS 4777.1. The network assesses each application and may approve it, approve it with an export limit, or ask for changes. Some networks offer a cheaper path if you limit exports: Ausgrid lets sites of 30 to 200kVA limit exports to 30kW for a lower application fee.
What changes at 30kW
Ausgrid's installer guidance notes that central protection is required by AS/NZS 4777.1 once a system exceeds 30kW[1]. AusNet runs a separate process for connections up to 30kW[2], and the same pattern applies across networks: above that, the application is assessed individually.
Export limits
Many business systems are approved with an export limit, sometimes zero. On a business site that matters less than at home if the load uses the solar during the day, and more if it doesn't. Ausgrid offers sites from 30 to 200kVA a lower application fee if they limit exports to 30kW[1]. See Ausgrid's options and, for homes and small sites, export limits by network.
What to ask before you sign
- Has the network application been lodged, and what export limit came back?
- Is central protection in the price?
- If the network approves less export than assumed, how does that change the savings in the proposal?
- Who pays for any network-required upgrades?
Get your business site assessed, by email
Commercial solar depends on your roof, your tariff, your load profile and your network, so every site is looked at individually. There is no online calculator for this, on purpose.
- 12 months of electricity bills, or your smart meter interval data (NEM12)
- The site address and what the business does
- Roof type and a few photos, if you have them
Or email olly@aussiesolarinfo.com with the subject "Commercial solar enquiry".
No installer pays to appear on this site. Nothing reaches an installer unless you ask.
Common questions
Does business solar over 30kW need network approval?
Yes. Systems over 30kW need written network approval before installation, and central protection under AS/NZS 4777.1.
Can I avoid network studies by limiting exports?
On some networks it lowers the cost. Ausgrid offers sites from 30 to 200kVA a lower application fee if exports are limited to 30kW.