Solar export limits by network in 2026: NSW, Victoria, Queensland and WA
Your solar export limit is set by the network company named on your bill, not your retailer, and the rules now differ a lot between them. Here is every major network in NSW, Victoria, Queensland and WA on one page, with a link to the details and sources for each.
Most networks now offer two kinds of connection: a fixed limit, which ranges from 1.5kW to 5kW depending on the network, and a flexible or dynamic limit of up to 10kW per phase that moves with the network and needs an internet-connected inverter. The table below shows each network's numbers in 2026.
Every network at a glance
| Network | State | Fixed or basic limit | Flexible or dynamic | Details and sources |
|---|---|---|---|---|
| Ausgrid | NSW | 3kW per system (fixed) | Up to 10kW per phase, down to 1.5kW per site | Read |
| Endeavour Energy | NSW | 1.5kW (Fixed Exports plan) | Up to 10kW per phase | Read |
| Essential Energy | NSW | Typically 5kW, lower in some areas | 1.5 to 5kW or 1.5 to 10kW per phase, from 23 Nov 2026 | Read |
| CitiPower and United Energy | VIC | Up to 1.5kW per phase (2026 to 2031) | Up to 10kW per phase | Read |
| Powercor | VIC | Up to 1.5kW per phase (2026 to 2031) | Up to 10kW per phase | Read |
| AusNet | VIC | Under 5kW per phase; under 3.5kW on SWER lines | Where a flexible limit applies | Read |
| Jemena | VIC | 5kW per phase while online; 0.5kW total offline | Planned, not yet live | Read |
| Energex | QLD | 5kW per phase; 2kW on SWER | Up to 10kW per phase, 1.5kW floor | Read |
| Ergon Energy | QLD | 5kW per phase; 2kW total on SWER | Moves with the network, 1.5kW floor | Read |
| Western Power (Perth) | WA | 1.5kW if not connected (from 1 May 2026) | Up to 5kW when managed under a retailer agreement | Read |
| Horizon Power | WA | Energy managed; hosting limits removed on most networks | Community Wave VPP | Read |
Summaries of each network's own published rules as of November 2026. The linked page for each network has the details and the original sources[1]. Your actual limit is set when your installer applies for connection.
What the numbers have in common
Three patterns run through almost every network: flexible limits need a CSIP-AUS compliant inverter and reliable internet; losing the internet drops you to a low fallback limit, usually 1.5kW and as low as 0.5kW on Jemena; and single-wire rural lines get lower limits. Ask your installer which connection type your quote assumes.
Export limits and export charges are different things
A limit caps how much you can send. A charge is what your retailer pays the network for midday exports above a free allowance. See Ausgrid, Endeavour, Essential, Victoria's networks and Queensland.
Why this pushes towards a battery
A tight limit wastes surplus you cannot send; a fallback limit wastes more if the internet drops. A battery stores what the limit would have cut off and uses it in the evening, when power is dearest. If your network gives you zero export, see zero export: what to do with a battery.
Get your own numbers
Two minutes of questions gets you your system size, what it should cost after rebates in your state, and what it saves, built on your roof and your usage. No installer sees anything unless you ask.
Run my numbers, freeNo installer buys placement or ranking here, and nothing reaches an installer unless you ask.
Common questions
What is the solar export limit in NSW?
It depends on the network: Ausgrid offers 3kW fixed or up to 10kW per phase flexible, Endeavour 1.5kW fixed or up to 10kW per phase flexible, and Essential typically 5kW fixed or a flexible range from 23 November 2026.
What is the solar export limit in Victoria?
CitiPower, United Energy and Powercor cap static limits at 1.5kW per phase for 2026 to 2031, with flexible exports up to 10kW per phase. AusNet allows under 5kW per phase, under 3.5kW on SWER lines. Jemena allows 5kW per phase while the inverter is online.
What is the solar export limit in Queensland?
5kW per phase on a basic connection on Energex and Ergon, 2kW on single-wire lines, or up to 10kW per phase on an Energex dynamic connection.
Sources
- Each network's own published rules, as cited on the linked network page on this site. Compiled 13 Nov 2026.